Bracknell Forest Council
Record of Decision
Work Programme Reference
|
|
1. |
TITLE: |
Capital Programme 2021/22 - Highways and Transport
|
|
||||||||
2. |
SERVICE AREA: |
Place, Planning & Regeneration
|
|
||||||||
3. |
PURPOSE OF DECISION
|
|
|||||||||
To approve the Highways and Transport Capital Programme for 2021/22 and its implementation
|
|
||||||||||
4 |
IS KEY DECISION |
Yes
|
|
||||||||
5. |
DECISION MADE BY: |
Executive
|
|
||||||||
6. |
DECISION:
|
|
|||||||||
RESOLVED that the overall Highways and Transport Capital Programme for 2021/22 is approved.
|
|
||||||||||
7. |
REASON FOR DECISION
|
|
|||||||||
The proposals in this report identify the current highway and transport priorities across the network. The schemes seek to facilitate transport in line with the Council’s Local Transport Plan 3 (LTP3) and ensure that the Council maintains the highway in as good a condition as resources allow, having due regard to the Council’s intervention policy based on network condition.
|
|
||||||||||
8. |
ALTERNATIVE OPTIONS CONSIDERED
|
|
|||||||||
1. Failure to approve the Highways and Transport Capital Programme would prevent the delivery of the Council’s obligations as a Highway Authority and be contrary to the position set out in the Council’s adopted Transport Policy (LPT3).
2. Given the reduction in highway maintenance funding levels in previous years, it would not be appropriate to allocate resources to anything other than the priorities identified through methodical and objective needs assessments.
|
|
||||||||||
9. |
DOCUMENT CONSIDERED: |
Report of the Director: Place, Planning & Regeneration
|
|||||||||
10. |
DECLARED CONFLICTS OF INTEREST: |
None
|
|||||||||
Date Decision Made |
Final Day of Call-in Period |
|
|||||||||
27 April 2021 |
4 May 2021 |
|
|||||||||